NEW QUESTION # 45
Time is running short and the Must Have requirements for the data entry screen of the web page, as recorded in the Prioritised Requirements List, are not going to be completed on time.
What action should the Project Manager take?
- A. Change the end date of the Timebox.
- B. Ensure that this issue is escalated to the project level roles.
- C. Accept that the Must Have requirements will not be delivered on time.
- D. Amend the end date in the Delivery Plan.
Answer: B
NEW QUESTION # 46
Using the project timeline given in the Project Scenario, answer the following question about application of Timeboxing on the Hoy Hall project.
Lines 1 to 5 in the table below consist of an assertion statement and a reason statement. For each line identify the appropriate option, from options A to E, that applies.
Each option can be used once, more than once or not at all.
Assertion :
1. All internal works to be assigned to Timber Tigers throughout the project should be consolidated into one Structured Timebox.
BECAUSE
The Investigation step within each Structured Timebox requires everyone working within the team to jointly agree how the requirements of the Timebox will be met.
2. Acceptance criteria for the front rooms to be developed in Timebox A should be described in detail and agreed during the Timebox Kick-Off BECAUSE The aim of the Investigation step within each Timebox is to complete as much of the development work as possible.
3. It is appropriate that both the Evolutionary Development phase and Deployment phase are shown in the first Project Increment.
BECAUSE
Each Timebox should comprise an Evolutionary Development phase and
Deployment phase.
4. It is appropriate that the outputs of Timebox C are scheduled for deployment at the end of the first Project Increment.
BECAUSE
A typical Timebox Plan should provide a schedule of high-level activities for the imminent Project Increment.
5. It is appropriate that Earth Excavations create a detailed plan of activities they will complete during Timebox C.
Reason
BECAUSE
The Solution Development Team is responsible for planning the detail of all the work of each Timebox.

Answer:
Explanation:
Explanation:
For each line, here is the appropriate option from A to E that applies:
* All internal works to be assigned to Timber Tigers throughout the project should be consolidated into one Structured Timebox.
* E. False (Assertion) False (Reason)
* Rationale: It is not practical or in line with Agile principles to consolidate all internal works into one Structured Timebox, as the work will likely need to be spread over multiple Timeboxes.
Additionally, the Investigation step involves agreeing on how to meet the requirements of the Timebox, not necessarily consolidating all work into one.
* Acceptance criteria for the front rooms to be developed in Timebox A should be described in detail and agreed during the Timebox Kick-Off
* B. True (Assertion) True (Reason) BUT the reason does not explain the assertion
* Rationale: While it is true that acceptance criteria should be agreed upon during the Timebox Kick-Off, the reason given is incorrect because the aim of the Investigation step is not necessarily to complete as much development work as possible but to plan and understand the work that will be carried out.
* It is appropriate that both the Evolutionary Development phase and Deployment phase are shown in the first Project Increment.
* A. True (Assertion) True (Reason) AND the reason explains the assertion
* Rationale: Each Timebox should indeed include both Evolutionary Development and a Deployment phase. This assertion and reason correctly align with the concept of Timeboxing in Agile.
* It is appropriate that the outputs of Timebox C are scheduled for deployment at the end of the first Project Increment.
* A. True (Assertion) True (Reason) AND the reason explains the assertion
* Rationale: The typical Timebox Plan does provide a schedule of high-level activities for the imminent Project Increment, which would include planning for deployment.
* It is appropriate that Earth Excavations create a detailed plan of activities they will complete during Timebox C.
* C. True (Assertion) False (Reason)
* Rationale: While it is true that Earth Excavations should create a detailed plan for their activities in Timebox C, the reason is incorrect as the Solution Development Team is not solely responsible for planning all work details within a Timebox. This task would typically be a collaborative effort involving all relevant parties.
NEW QUESTION # 47
Using the Project Scenario and the additional information provided for this question in the Scenario Booklet, answer the following question about the responsibilities of the roles in the Agile team.
Lines 1 to 5 in the table below consist of an assertion statement and a reason statement. For each line identify the appropriate option, from options A to E, that applies.
Each option can be used once, more than once or not at all.

Assertion
* The Marketing Director, in the role of Business Visionary, is empowered to overrule cost restrictions advised by the Chief Accountant, who is appointed as Business Ambassador.
BECAUSE
The Project-level roles are responsible for directing, managing and co- ordinating the project.
* The Procurement Manager is an appropriate representative of the end user of the solution.
BECAUSE
The Business Ambassador should be empowered to make decisions within
the boundaries of their role, without referral to higher authorities outside the Solution Development Team.
* The other specialist gardening team members from Earth Excavations would be suitable as Solution Developers, assigned alongside the Head Landscape Gardener.
BECAUSE
Extra Solution Developers can provide a supporting role for a Lead
Developer.
* The 'Hoy for Hoy Hall' Action Group members should be assigned as Business Ambassadors.
BECAUSE
The Business Ambassador is responsible for ensuring that business needs are properly analysed.
* The Project Manager should plan the communication needed between the Marketing Director, in the role of Business Visionary, and the 'Hoy for Hoy Hall' Action Group.
BECAUSE
The Business Visionary is responsible for promoting the business vision to all interested parties.
Answer:
Explanation:
Explanation:
Here are the appropriate options for each assertion and reason combination:
* The Marketing Director, in the role of Business Visionary, is empowered to overrule cost restrictions advised by the Chief Accountant, who is appointed as Business Ambassador.
* C. True (Assertion) False (Reason)
* Rationale: While the Business Visionary may have the authority to make strategic decisions that could overrule cost restrictions, the reason given relates to project-level roles directing the project, not to the authority to overrule cost-related advice.
* The Procurement Manager is an appropriate representative of the end user of the solution.
* B. True (Assertion) True (Reason) BUT the reason does not explain the assertion
* Rationale: The Procurement Manager, as part of the operational team, could represent the end user. However, the reason given talks about the empowerment of the Business Ambassador, which does not directly explain why the Procurement Manager is a representative of the end user.
* The other specialist gardening team members from Earth Excavations would be suitable as Solution Developers, assigned alongside the Head Landscape Gardener.
* A. True (Assertion) True (Reason) AND the reason explains the assertion
* Rationale: Specialist gardening team members would be suitable as Solution Developers, providing support to the Lead Developer, which is a common practice in Agile teams.
* The 'Hoy for Hoy Hall' Action Group members should be assigned as Business Ambassadors.
* D. False (Assertion) True (Reason)
* Rationale: While the Business Ambassador should ensure that business needs are analyzed, the
'Hoy for Hoy Hall' Action Group members being assigned as Business Ambassadors is not necessarily true as they are external stakeholders and not necessarily equipped to represent the business internally on a project.
* The Project Manager should plan the communication needed between the Marketing Director, in the role
* of Business Visionary, and the 'Hoy for Hoy Hall' Action Group.
* A. True (Assertion) True (Reason) AND the reason explains the assertion
* Rationale: The Project Manager typically has the responsibility to plan and manage communication between the project team and external stakeholders, and the Business Visionary's role includes promoting the business vision to interested parties, which includes the 'Hoy for Hoy Hall' Action Group.
NEW QUESTION # 48
Using the Project Scenario and the additional information provided for
this question in the Scenario Booklet, answer the following question
about assigning the Agile Project Management team roles within this
project.
Lines 1 to 5 in the table below consist of an assertion statement and a reason statement. For each line identify the appropriate option, from options A to E. that applies. Each option can be used once, more than once or not at all.
Answer:
Explanation:
Explanation:
The activities from Column 1 should be performed in the following steps from Column 2, according to the iterative development process:
* Create the data entry screen for entering coffee bar details needed for a quotation.Selection: B.
ActionExplanation: Creating the data entry screen is part of the 'Action' step in iterative development, where the actual product or a part of it is being constructed.
* Enter numbers into a text-only field to see how the web page behaves.Selection: A. Thought Explanation: Testing how the web page behaves by entering data is part of the 'Thought' step, which includes reviewing and evaluating the work done, testing, and reflecting on the outcomes.
* Discuss the requirements of the new coffee bar insurance web page and agree which data fields are important.Selection: C. ConversationExplanation: Discussing and agreeing on the requirements is part of the 'Conversation' step, which involves interactions between team members and stakeholders to understand and define what needs to be built.
NEW QUESTION # 49
Xan Insurance Company is a friendly company with no separate private offices for individual managers. Staff members prefer to wander around the office space and have one-to-one chats rather than use email or have lots of meetings.
What action should the Project Manager take when planning for effective communication throughout the Web project?
- A. Mandate the use of email so that all communications are recorded for future reference.
- B. No action is required as the existing form of spontaneous informal
communication is suitable for all project level and Solution Development Team members. - C. As this is already common practice, assume all Solution Development
Team members have effective communication skills. - D. Identify those individuals with power and influence over the project and what information they require.
Answer: D
Explanation:
The most effective action the Project Manager should take to ensure effective communication throughout the Web project at Xan Insurance Company is:
A: Identify those individuals with power and influence over the project and what information they require.
In any project, especially within an Agile framework, understanding the stakeholders' landscape is crucial for effective communication management. Identifying key individuals with power and influence over the project helps tailor communication strategies to ensure that critical information is shared appropriately, decisions are facilitated efficiently, and stakeholder engagement is maintained. While the company's culture of informal communication can be advantageous for day-to-day interactions, structured communication is essential for project governance, risk management, and decision-making processes. This approach allows the Project Manager to ensure that all stakeholders are kept informed according to their needs and the project's requirements, balancing the informal communication culture with the need for formal communication where necessary.
NEW QUESTION # 50
Column 1 is a list of actions taken within the project. For each action in Column 1, select from Column 2 the iterative development activity that the action represents. Each selection from Column 2 can be used once, more than once or not at all.
Column 1:
1.The Solution Development Team cleared and prepared the area, ready for the bar infrastructure to be installed.
2.The Gardener decided the order in which the flowers would be planted in the borders and jotted it down in a notebook.
3.Before the Solution Development Team built the infrastructure for the bar area, the Architect pointed out what was required.
4.The Architect checked with the decorators that tasks had been completed to a satisfactory standard, and agreed a list of items that needed further coats of paint or cleaning up.
5.The Gardener began planting the borders and has placed an order for further bulbs to complete this task.
Column 2:
A) Thought
B) Action
C) Conversation
Answer:
Explanation:
Explanation:
For each action in Column 1, here is the iterative development activity that the action represents from Column
2:
* The Solution Development Team cleared and prepared the area, ready for the bar infrastructure to be installed.
* B. Action
* The Gardener decided the order in which the flowers would be planted in the borders and jotted it down in a notebook.
* A. Thought
* Before the Solution Development Team built the infrastructure for the bar area, the Architect pointed out what was required.
* C. Conversation
* The Architect checked with the decorators that tasks had been completed to a satisfactory standard, and agreed a list of items that needed further coats of paint or cleaning up.
* C. Conversation
* The Gardener began planting the borders and has placed an order for further bulbs to complete this task.
* B. Action
NEW QUESTION # 51
Which 2 statements represent appropriate entries for the Prioritised
Requirements List?
- A. Creation of a new coffee shop insurance product on the existing website is expected to increase the insurance company's revenues by up to 10% per week.
- B. An assessment will be made of the effectiveness of the techniques used on the project, in line with the principles of Agile Project Management.
- C. The Business Visionary will provide a formal acceptance of the coffee shop insurance product.
- D. Further website developments to allow existing customers to access
services online are NOT to be included within the scope of this project. - E. All correspondence sent to coffee shop owners by the new system should contain the XAN logo in the top left hand corner of the page.
Answer: D,E
NEW QUESTION # 52
Once the change of priority has been approved, who is then responsible for including the requirement for a secondary exit from the upstairs of the building to the Timebox Plan for Timebox B?
- A. Project Manager and Architect, in the role of Technical Co-ordinator.
- B. Team Leader.
- C. Marketing Director, in the role of Business Visionary.
- D. Architecture Angels' Senior Management Team.
Answer: B
NEW QUESTION # 53
Answer the following questions about the acceptance criteria within the project.
Decide whether the approach to setting and using acceptance criteria has been applied appropriately and select the response that supports your decision.
When specifying high-level prioritised requirements during Foundations, the Business Visionary has suggested that acceptance criteria for the requirement to "temporarily weatherproof the roof" should NOT be set until Solution Development Timebox A.
Is this an appropriate approach to setting high-level acceptance criteria?
- A. No, because by the end of Foundations the quality expectations and overall acceptance criteria for at least the first increment should have been set, and high-level acceptance criteria set for later increments.
- B. Yes, because acceptance criteria are NOT set before the Timeboxed work is started.
- C. Yes, because the Local Planning Authority Officer will set the acceptance criteria.
- D. No, because a Review Session should have been scheduled during Feasibility to enable the Solution Development Team to validate their understanding of the Local Planning Authority Officer's expectations.
Answer: A
Explanation:
C: No, because by the end of Foundations the quality expectations and overall acceptance criteria for at least the first increment should have been set, and high-level acceptance criteria set for later increments.
Rationale:
In Agile Project Management, it's important to establish high-level acceptance criteria early in the project to guide development and ensure that the solution meets the business needs and quality expectations. The Foundations phase is when the project's scope, objectives, and methods are defined, including the acceptance criteria for the first increment and at a high level for subsequent increments. This ensures that everyone has a clear understanding of what "done" looks like before development begins, reducing the risk of misalignment and rework.
NEW QUESTION # 54
When preparing for the workshop, which 2 items should the Workshop Facilitator be provided with?
- A. Hints and tips on how to influence and persuade others.
- B. Empowerment to discuss any wider project issues that may arise during the workshop.
- C. Background to the disagreement and the reasons for this.
- D. A step-by-step guide to running an effective workshop.
- E. An understanding of the decision-making process.
Answer: C,E
Explanation:
The two items that the Workshop Facilitator should be provided with when preparing for the workshop are:
*B. An understanding of the decision-making process. This will help the facilitator guide the discussion and help the group reach a consensus.
*C. Background to the disagreement and the reasons for this. This will help the facilitator understand the context of the disagreement and facilitate a more effective discussion.
Please note that while hints and tips on how to influence and persuade others (option A), empowerment to discuss any wider project issues that may arise during the workshop (option D), and a step-by-step guide to running an effective workshop (option E) could be helpful, they are not as crucial as understanding the decision-making process and the background to the disagreement for this specific workshop.
NEW QUESTION # 55
The Marketing Director has insisted that detailed requirements for the new coffee bar insurance web pages should be clearly defined in the early phases of the project.
What action should the Project Manager take?
- A. Capture the Marketing Director's requirements in detail but leave the input of others until later in the project.
- B. Agree to document the finite details of each requirement to ensure the web developers can accurately estimate the effort required to fulfil them.
- C. Refuse to discuss any detailed requirements in the early phases.
- D. Hold an early discussion to the level of detail necessary to establish a shared understanding of what is required.
Answer: D
NEW QUESTION # 56
Which 2 statements explain why the Timber Tigers' Site Manager would be an appropriate Solution Developer?
- A. Closely manages the building team so that they consistently produce high-quality work.
- B. Is empowered by Timber Tigers' management to make decisions on the building work.
- C. An experienced builder who is good at turning a brief into a practical design.
- D. Is able to represent the team in all daily meetings.
- E. Accustomed to bringing in contract staff for short periods of time.
Answer: A,C
NEW QUESTION # 57
The Close Out of Timebox B was completed as scheduled, but the Could Have requirement of tiled walls in the bathrooms was NOT delivered within this period, with the agreement of the team.
Which Agile principle MOST influences this course of action?
- A. Build incrementally from firm foundations.
- B. Develop iteratively.
- C. Deliver on time.
- D. Never compromise quality.
Answer: C
NEW QUESTION # 58
Which 2 actions should the Project Manager take to implement the new Must Have requirement?
- A. Add the tasks required to develop the new financial transaction functionality to the Delivery Plan.
- B. Check for any documented standards which need to be applied to the
development of online financial transaction functionality. - C. Update the Delivery Plan to show the new financial transaction functionality as a deliverable.
- D. Source and hire a web developer with experience in developing online financial transaction functionality.
- E. Consolidate and circulate an agenda for the workshop.
Answer: A,C
Explanation:
To effectively implement the new Must Have requirement for financial transaction functionality on the coffee shop insurance product website, the Project Manager should focus on actions that align with their role in planning, execution, and team coordination. The following actions are most appropriate for the Project Manager:
Selected Actions for the Project Manager:
B; Add the tasks required to develop the new financial transaction functionality to the Delivery Plan.
C; Update the Delivery Plan to show the new financial transaction functionality as a deliverable.
B: Integrating the tasks necessary for developing the new functionality into the Delivery Plan is crucial. This ensures that all project activities are accounted for and scheduled, which helps in managing the project's timeline and resources effectively.
C: Reflecting the new financial transaction functionality as a deliverable in the Delivery Plan is important for clarity and focus. It signifies the inclusion of this functionality as a critical component of the project's scope, guiding the team's efforts and priorities.
Why Other Actions Are Less Suitable:
A: While ensuring adherence to documented standards is important, it is typically a collaborative effort involving the Technical Coordinator and Solution Development team, in addition to the Project Manager, to ensure technical compliance.
D: Sourcing and hiring specific expertise, such as a web developer skilled in online financial transactions, is indeed part of the Project Manager's responsibilities. However, the actions related to the Delivery Plan (options B and C) are more directly aligned with the immediate steps for implementing a new requirement in the project's scope.
E: Consolidating and circulating an agenda for the workshop is a logistical task that the Project Manager might oversee or delegate. However, the actions related to planning and updating the Delivery Plan are more critical to the successful implementation of the new requirement.
NEW QUESTION # 59
Answer the following questions about the acceptance criteria within the project.
Decide whether the approach to setting and using acceptance criteria has been applied appropriately and select the response that supports your decision.
The objective of Solution Development Timebox B is to ensure that the front and east wings are finished and approved. The Project Manager has pointed out that acceptance criteria for this part of the solution need to be agreed.
Is this an appropriate action related to acceptance criteria?
- A. No, because the acceptance criteria for the Solution Development Timebox are just the amalgamation of the individual requirements' acceptance criteria, with nothing extra.
- B. Yes, because it will be easier to set acceptance criteria for the Solution Development Timebox as a whole, rather than setting specific acceptance criteria for each individual requirement.
- C. Yes, because this will allow the Solution Development Team to focus on the quality of the Solution Development Timebox's deliverable as a whole, in order to keep focus on the business need.
- D. No, because the Solution Development Timebox objective will change if any new requirements emerge or any lower priority requirements are de-scoped.
Answer: C
Explanation:
A; Yes, because this will allow the Solution Development Team to focus on the quality of the Solution Development Timebox's deliverable as a whole, in order to keep focus on the business need.
Rationale:
Setting acceptance criteria for the overall deliverables of a timebox is a key practice in Agile to ensure that the work meets the business objectives and quality expectations. It helps the Solution Development Team to understand what is required for the deliverables to be considered complete and acceptable. This aligns with the Agile principle of delivering quality and maintaining a constant pace of development. It also ensures that all team members are aligned on the goals and can focus on delivering value in line with business needs.
NEW QUESTION # 60
Answer the following question about how risks will be reduced on the Hoy Hall Hotel project through successful application of the DSDM Principles.
Column 1 lists a selection of project risks identified on the Hoy Hall Hotel project. Column 2 is a list of the DSDM Principles. For each risk in Column 1, select from Column
2 the DSDM Principle which, if applied appropriately, would MOST help to reduce or mitigate that risk.
Each selection from Column 2 can be used once, more than once or not at all.

Answer:
Explanation:
Explanation:
Here are the DSDM Principles that would most help to reduce or mitigate the listed risks:
* The 'Hoy for Hoy Hall' Action Group may cause delay to the project if they are not kept updated on how the finished rooms are going to look.
* G. Communicate continuously and clearly
* Timber Tigers will ensure that the front rooms are finished and approved by the end of Timebox A.
* E. Build incrementally from firm foundations
* The Architecture Angels IT support team may require more detail up front in order to approve the initial design for the new online reservation system.
* A. Focus on the business need
* The morale of the Solution Development Team may be adversely affected if the external web design specialist is not a team player.
* C. Collaborate
* Empowering the Solution Development Team to manage themselves on a day-to-day basis may result in the Project Manager losing sight of what activities are being carried out, by whom and when.
* H. Demonstrate control
NEW QUESTION # 61
Using the Project Scenario and the additional information provided for this question in the Scenario Booklet, answer the following question about the responsibilities of the roles in the Agile team.
Lines 1 to 5 in the table below consist of an assertion statement and a reason statement. For each line identify the appropriate option, from options A to E, that applies.
Each option can be used once, more than once or not at all.
Assertion
* The Marketing Director, in the role of Business Visionary, is empowered to overrule cost restrictions advised by the Chief Accountant, who is appointed as Business Ambassador.
BECAUSE
The Project-level roles are responsible for directing, managing and co- ordinating the project.
* The Procurement Manager is an appropriate representative of the end user of the solution.
BECAUSE
The Business Ambassador should be empowered to make decisions within
the boundaries of their role, without referral to higher authorities outside the Solution Development Team.
* The other specialist gardening team members from Earth Excavations would be suitable as Solution
* Developers, assigned alongside the Head Landscape Gardener.
BECAUSE
Extra Solution Developers can provide a supporting role for a Lead
Developer.
* The 'Hoy for Hoy Hall' Action Group members should be assigned as Business Ambassadors.
BECAUSE
The Business Ambassador is responsible for ensuring that business needs are properly analysed.
* The Project Manager should plan the communication needed between the Marketing Director, in the role of Business Visionary, and the 'Hoy for Hoy Hall' Action Group.
BECAUSE
The Business Visionary is responsible for promoting the business vision to all interested parties.
Answer:
Explanation:
Explanation:
Here are the appropriate options for each assertion and reason combination:
* The Marketing Director, in the role of Business Visionary, is empowered to overrule cost restrictions advised by the Chief Accountant, who is appointed as Business Ambassador.
* C. True (Assertion) False (Reason)
* Rationale: While the Business Visionary may have the authority to make strategic decisions that could overrule cost restrictions, the reason given relates to project-level roles directing the project, not to the authority to overrule cost-related advice.
* The Procurement Manager is an appropriate representative of the end user of the solution.
* B. True (Assertion) True (Reason) BUT the reason does not explain the assertion
* Rationale: The Procurement Manager, as part of the operational team, could represent the end user. However, the reason given talks about the empowerment of the Business Ambassador, which does not directly explain why the Procurement Manager is a representative of the end user.
* The other specialist gardening team members from Earth Excavations would be suitable as Solution Developers, assigned alongside the Head Landscape Gardener.
* A. True (Assertion) True (Reason) AND the reason explains the assertion
* Rationale: Specialist gardening team members would be suitable as Solution Developers, providing support to the Lead Developer, which is a common practice in Agile teams.
* The 'Hoy for Hoy Hall' Action Group members should be assigned as Business Ambassadors.
* D. False (Assertion) True (Reason)
* Rationale: While the Business Ambassador should ensure that business needs are analyzed, the
'Hoy for Hoy Hall' Action Group members being assigned as Business Ambassadors is not necessarily true as they are external stakeholders and not necessarily equipped to represent the business internally on a project.
* The Project Manager should plan the communication needed between the Marketing Director, in the role of Business Visionary, and the 'Hoy for Hoy Hall' Action Group.
* A. True (Assertion) True (Reason) AND the reason explains the assertion
* Rationale: The Project Manager typically has the responsibility to plan and manage communication between the project team and external stakeholders, and the Business Visionary's role includes promoting the business vision to interested parties, which includes the 'Hoy for Hoy Hall' Action Group.
NEW QUESTION # 62
The Business Ambassador assigned to the project is only available 2 days a week. The Project Manager has stated that the Investigation stage for each Timebox should, where possible, be planned around the availability of the Business Ambassador.
Is this an appropriate application of the DSDM lifecycle?
- A. Yes, because this is where any final quality control checks should be carried out to ensure all products meet the business need.
- B. No, because Timeboxes are only used during Evolutionary Development and at this point the Business Ambassador is NOT required.
- C. Yes, because the Investigation stage of a Timebox requires intense
engagement with the Business Ambassador. - D. No, because it is the Refinement stage of a Timebox that requires intense engagement with the Business Ambassador.
Answer: C
Explanation:
In the context of the DSDM lifecycle, the Investigation stage of a Timebox is crucial for understanding and defining the work to be done, which often necessitates close collaboration with business representatives such as the Business Ambassador. This role is integral in ensuring that the project's outputs align with business needs and priorities. Planning the Investigation stage around the Business Ambassador's availability facilitates this essential engagement, making it a suitable application of the DSDM lifecycle. This approach ensures that the project benefits from the Business Ambassador's insights and guidance during critical early phases, contributing to a stronger alignment between project deliverables and business requirements.
References:The Agile Project Management (AgilePM) framework, which incorporates DSDM principles, emphasizes the importance of collaboration between the project team and business stakeholders throughout the project lifecycle. The involvement of the Business Ambassador during the Investigation stage is particularly valuable for clarifying requirements, setting priorities, and ensuring that the project remains focused on delivering business value, in line with Agile and DSDM practices.
NEW QUESTION # 63
Using the Project Scenario, answer the following question about the activities in the Agile project lifecycle.
Lines 1 to 5 in the table below consist of an assertion statement and a reason statement. For each line identify the appropriate option, from options A to E, that applies. Each option can be used once, more than once or not at all.
Assertion:-
1. The rooms and facilities must be deployed into live use at the end of each Timebox.
BECAUSE
Reason:
Evolutionary Development and Deployment must be combined in a Timebox where the integration of several teams is required.
2. The tasks associated with each Solution Development Timebox should be included in the Delivery Plan.
BECAUSE
Reason:
A typical Delivery Plan will provide a schedule of Timeboxes and any other high level activities for the imminent Project Increment.
3. The development approach should have been agreed during Foundations.
BECAUSE
Reason:
The Development Approach Definition must be created before Evolutionary Development can commence.
4. The resources from Timber Tigers and Earth Excavations should have been engaged before the start of Evolutionary Development.
BECAUSE
Reason:
Commitment to delivery is based on pre-agreed resource levels at the project level.
5. A final Deployment phase should be held after Timebox C has completed.
BECAUSE
Reason:
The Deployed Solution is assessed post-project to confirm whether the expected benefits have been achieved.

Answer:
Explanation:
Explanation:
Agile Practitioner
For each line, here is the appropriate option from A to E that applies:
* The rooms and facilities must be deployed into live use at the end of each Timebox.
* D. False (Assertion) True (Reason)
* Rationale: While Evolutionary Development and Deployment can be combined in a timebox, it is not necessary that the rooms and facilities must be deployed into live use at the end of each timebox. Deployment into live use typically occurs after several timeboxes when the product is ready for release.
* The tasks associated with each Solution Development Timebox should be included in the Delivery Plan.
* A. True (Assertion) True (Reason)
* Rationale: The Delivery Plan should outline the schedule of timeboxes and include the high-level activities planned for the upcoming project increment, which encompasses the tasks for each Solution Development Timebox.
* The development approach should have been agreed during Foundations.
* A. True (Assertion) True (Reason)
* Rationale: The development approach is indeed something that should be agreed upon during the Foundations phase, as the Development Approach Definition sets the stage for how Evolutionary Development will proceed.
* The resources from Timber Tigers and Earth Excavations should have been engaged before the start of Evolutionary Development.
* C. True (Assertion) False (Reason)
* Rationale: It is true that resources should be engaged before Evolutionary Development starts to ensure commitment and resource availability. However, the commitment is typically based on the detailed planning and agreements made during Foundations, not solely on pre-agreed resource levels at the project level.
* A final Deployment phase should be held after Timebox C has completed.
* E. False (Assertion) False (Reason)
* Rationale: Deployment phases are usually not a one-time, final phase but occur incrementally as part of the timeboxed development. Additionally, the assessment of whether the expected benefits have been achieved is part of the benefits realization process and not necessarily the sole reason to have a final Deployment phase post-Timebox C.
NEW QUESTION # 64
......
APMG-International AgilePM-Practitioner Exam Syllabus Topics:
| Topic | Details |
|---|---|
| Topic 1 |
|
| Topic 2 |
|
| Topic 3 |
|
| Topic 4 |
|
AgilePM-Practitioner Exam Dumps, AgilePM-Practitioner Practice Test Questions: https://www.practicetorrent.com/AgilePM-Practitioner-practice-exam-torrent.html
Free AgilePM-Practitioner Study Guides Exam Questions and Answer: https://drive.google.com/open?id=1R6bqtjBrSgc3yBLlmTGitn750T3EyqvY